Warning: Use of undefined constant X - assumed 'X' (this will throw an Error in a future version of PHP) in /home/tneutron/public_html/wp-content/themes/jarida_disabled/functions.php on line 7
" /> Maintain Pole Substation Installation – TN Blogs
Notice: Undefined index: font in /home/tneutron/public_html/wp-content/themes/jarida_disabled/functions/common-scripts.php on line 150

Notice: Undefined index: font in /home/tneutron/public_html/wp-content/themes/jarida_disabled/functions/common-scripts.php on line 150

Notice: Undefined index: font in /home/tneutron/public_html/wp-content/themes/jarida_disabled/functions/common-scripts.php on line 150
Home > Distribusi Tegangan Rendah > Maintain Pole Substation Installation

Maintain Pole Substation Installation

Officer:

1. Supervisor 1
2. Implementing 2 people

Coordination:
1. Maintenance Planning Coordinator
2. Maintenance Coordinator JTR
3. Coordinating Supplies
4. Maintenance Asman
5. Customers

Work Equipment:
1. Set Toolkit.
2. Tang Press.
3. Hammer 3 Kg.
4. Hoe, Tali.
5. Saws Iron
6. Stainless Steel Fasteners

Measuring equipment:
1. Earth Tester

EQUIPMENT K-3:
1. Helmet Safety.
2. Rubber Shoes.
3. Leather Gloves.
4. Work Clothes.
5. a safety belt
6. P-3K

Materials / Tools:
1. Ground Rod
2. BC 50 mm
3. Grounding Clamps
4. Galvanized Pipe
5. Stainless Steel Strap and Buckles Stopping
6. CCO (Connector Al / Cu)

Work Procedures:
1. Implementation of maintenance on the basis of the PK of the authorized supervisor.
2. Make checks to the location, to the basic preparation work.
3. Prepare a working tool, a tool of K-3 and materials necessary work.
4. Confirm the date and time of execution of maintenance.
5. Carry out work in accordance with the agreed schedule.
6. Finish carrying out the work, immediately report to the command post.
7. Create a written report to the supervisor who menugsakan.

Work Steps:
1. The executive officer receives the PK of Asman Distribution to perform system maintenance Earthing (grounding) Low Voltage Network.
2. Prepare Working Tools, Measurement, Tools K-3, Materials and Tools Work in accordance with the requirements.
3. When the officer arrived at the location, use the Tools K-3 post signs warning to the public and subsequently report to the command post that officers will perform system maintenance earthing (grounding) JTR.
4. Check the connections and grounding wire grounding system visually.
5. If there are abnormalities such broken or missing then replace it with a new conductor by connecting the grounding wire to the neutral JTR while the other end is not connected to the Ground let Rod.
6. Perform Resistivity measurements Grounding / Ground Rod accordance with the instruction manual, and record the value of prisoners in Form BA.
7. If the resistance value measurement results> 5 Ohm do with adding or deepening Ground Rod. Or by other methods.
8. Perform repeated measurements and record the grounding resistance value in the form of Minutes (BA).
9. Do penyembungan ka wat to Ground Rod grounded using grounding clamps.
10. Check the results of the work and make sure that the network personnel and equipment in a safe condition.
11. Report to the post that the maintenance work has been completed.
12. Clean up work equipment & K-3 and warning signs to alert the public as well as clean the work area.
13. Create Report and Minutes of the implementation of the grounding system maintenance work.
14. Reports and Minutes of the completion of the work submitted to Asman Distribution.