Implement the provisions of the Air Line Construction Medium Voltage (according PUIL 2000)
∧ Conductor bare air in pairs, stretched over supporting poles with insulators.
Crosses ∧ airways with telecommunication channels with spacing
– Conductor bare within 1 meter, 1 meter crossed.
– Conductor insulated lined 1 meter, 1 meter crossed.
Installation ∧ airways TM with telecommunication channels must be greater than the distance of 2.5 meters.
Mounting on a pole ∧ airways airways TM with TR (underbuilt) at every 3 pole must be in pairs earthing conductor is connected with the neutral conductor.
∧ Distance secure airway against the parts are connected with the earth is a minimum of 5 cm + 2/3 x kV system. .
But safe distance line on the general environment is determined by the local government.
∧ distance between two conductive airways TM (% 20 kV) of at least 60 cm.
The minimum distance deflection ∧ conductor to ground is 6 meters.